History:
Building 34 is located within a larger facility belonging to Siemens in Erlangen. It was constructed in the 1970s and has been used as a laboratory building for many years. Due to extensive renovations, the fire protection measures needed to be improved and modernised.
Initial situation:
Because of structural changes and changes in use, areas in a corridor around the circumference needed to serve as an emergency corridor and escape route under building law. In the past, this corridor was not suited for use as an escape route, since there were different fire loads and fire hazards in the ceiling and behind the metal wall covering.
Cables, ventilation ducts and pipelines carrying different media were installed in the ceiling. Electrical distributors, storage areas, and cables, ventilations, and pipelines were installed behind the wall coverings. All of these elements increased the complexity of the structure, which was not easily reduced.
These installations and storage areas needed to be separated in accordance with modern technical requirements.
Solution:
To create an escape corridor (escape route) clear of the different fire loads, a fire-resistant wall construction system from PRIORIT was designed made of non-combustible panels.
A total of 19 alcoves needed to be made fire-resistant and covered with the wall system.
The wall system was designed in different shapes (I, L and U-shapes) in widths of 1,215 to 10,600 mm.
Three steps were required to achieve the protective goal:
Design:
The entire solution was developed and coordinated in the implementation phase by Spie, Erlangen, in collaboration with the companies involved in the project.
A PRIORIT project manager conducted a site inspection and took careful measurements. The information was used to create detailed drawings showing the required height of the steel girders to be installed.
After the steel girders were mounted, the PRIORIT installation team was able to install the custom pre-fabricated wall systems.
The existing wall coverings, flooring and floor tracks (metal) in the system area were removed as an on-site service. After the removal was completed, the plastered framing needed to be made flush with the wall once again.
Likewise, a fire-resistant covered steel girder was installed on site at a height of 2,450 mm to which the wall system was connected at the top.
Conclusion:
The custom planned wall systems with integrated inspection opening closures were an ideal solution for the structural situation. All key areas remain fully accessible, while ensuring fire protection requirements are met.
The assembly process was smooth and clean, thanks to careful advance planning. The custom pre-fabricated wall and door elements, just 42 mm thick, were installed quickly and almost dust-free. The developer and users alike are satisfied with the visually appealing overall solution.
Project data | |
---|---|
Project location: | Erlangen |
Building: | Siemens research centre, laboratory building |
Year of construction: | 2021 |
Solution: | PRIODOOR EXT inspection closures; PRIOWALL wall system |
Material: | Non-combustible panel with surface coating, classification A2 – s1, d0 |
Fire-resistance rating: | 30 minutes |
Protective target: | Fire-resistant separation of fire loads of different kinds (electrical distributor units, storage for laboratory materials, gas canisters, supply lines carrying different materials) |
Special features: | PRIORIT elements were constructed in I, L, and U shapes |
Developer: | Siemens AG |
Planning & construction management | Spie Erlangen |
Photos: | Daniel Schvarcz |